 A Level 1 interconnection request will be used for <10 KVA (or kW) AC. The hyperlinks below can be utilized for standard residential Distributed Generation connection requests. Below is a checklist of steps to help guide members with their DG project.

  • Level 1 Application (systems <10 kW) 
    • Includes specs of DG system and targeted commission date, etc. (requires Engineering approval)
    • Fundamental 1-Line Diagram showing interconnection
    • Site Plan/Drawing showing proposed location of DG system/DG Disconnect (properly placarded)
    • Application Fee Payment
  • Signed Contract (pending application approval)
  • Member notifies JCE in advance of construction completion (for Technician scheduling)
  • Certificate of Completion
    • Signed by both parties as a result of successful witness test/commissioning (per JCE testing criteria)
    • JCE Technician installs bi-directional meter
  • NOTE:  Please confirm your proposed installation meets all applicable(JCE, code, zoning, etc.) requirements prior to approval/installation

Level 1 Flowchart

Net Metering Infographic

Review Level Fee

Level 1 Application and Contract

Certificate of Completion 

Wiring Statement

*For questions and more information about our Distributed Generation program, contact Jo-Carroll Energy at

800-858-5522 or email dg@jocarroll.com

 

Powered by Touchstone Energy Cooperatives Logo